Renovate or demolish: what to do with a 1980s or 1990s villa in Marbella

Four checks that decide whether to renovate the house you have or start from scratch.

Published on 20 November 2026 · Bóveda Arquitectura

This is not a question of taste. Before choosing, you need to know what you have, what today's planning code lets you build and what the regulations demand in each case.

Many of the villas in estates such as Nueva Andalucía, Guadalmina or El Paraíso were built thirty or forty years ago. They often sit on plots and in locations that would be hard to find today, inside a house that no longer suits the way people live: compartmentalised rooms, little connection with the garden, windows and insulation from another era.

Anyone who buys or inherits one of these houses ends up asking the same question: should I renovate it, or knock it down and build a new one? The answer rarely depends on taste. It depends on four things, best checked in this order.

1. Which parts of the house are legal

Before talking about design you need to know what was built with a licence. In villas of this age it is common to find enclosed porches, extensions, outbuildings or pools that were never regularised. This is checked by comparing the original licence and project, the first occupation licence if there is one, the Land Registry extract and the cadastral description with what actually stands on the plot.

If part of the house was built without a licence and the legal period for the town hall to act has expired, in Andalucía it can be declared asimilado a fuera de ordenación (AFO), roughly “treated as non-conforming”. Two things are worth knowing: AFO status is not the same as legalisation, and on these buildings the law only allows conservation and refurbishment works that do not increase the footprint or the built volume (article 174 of Andalusian Law 7/2021, known as LISTA).

That changes the decision. A house with irregular parts may have limited scope for renovation, and if you demolish it, those square metres can only be rebuilt if the current plan allows them.

2. How much today's plan lets you build

Many villas were designed under planning rules different from today's. The house may have more built area than the plot now allows, sit closer to the boundary than the current setback requires, or exceed the permitted height. When a legally built house no longer fits the current plan, it is said to be fuera de ordenación (non-conforming).

The practical rule is simple: whatever you demolish is rebuilt under today's rules. If the current plan is stricter than the old one, demolishing can cost you square metres, views or a whole floor. If it is more generous, a new house can use buildability the existing one leaves unused. The works allowed on a non-conforming house are set by each municipality's plan, so it has to be read for that specific plot.

3. The condition of the structure and services

The structure, foundations and earthworks are among the most expensive items in a house, and a renovation that keeps them starts with an advantage. But only if they are sound. Before deciding, a technical inspection should check:

  • Cracks, settlement and the condition of the foundations, especially on sloping or filled plots.
  • Floor slabs and beams: corroded reinforcement, deflection or persistent damp.
  • Roofs and waterproofing, which in villas of this age have usually reached the end of their useful life.
  • Electrical, plumbing, drainage and air-conditioning installations, which almost always need replacing entirely.

If the structure needs major reinforcement and the project changes the layout completely, the cost advantage of renovating shrinks considerably.

4. What the building code requires in each case

A new house must comply in full with the Código Técnico de la Edificación, Spain's building code, including its nearly zero-energy building requirements. In a renovation the rules are more flexible and depend on the extent of the work: if more than 25% of the thermal envelope (façades, roof and windows) is renewed, the house's combined heating and cooling demand must fall below that of a reference building; if less is renewed, each element that is replaced must meet minimum insulation values. A renovation of that scope also requires a new energy performance certificate.

In other words, a well-planned renovation can greatly improve efficiency without the demands of a new build, but a new house goes further on comfort and consumption from the outset.

Licences and timing

Here renovation usually has the edge. In Andalucía, works on existing buildings on consolidated urban land that comply with the plan, or are legally non-conforming, can be processed with a declaración responsable (a self-certified notice to the town hall) as long as they do not change the footprint, height, buildability or number of dwellings (article 138 of LISTA). Once the notice is filed with complete documentation, work can start without waiting for the town hall to grant a licence.

A new house, by contrast, needs a building licence, and demolishing the existing one has its own procedure. If the renovation extends the house or affects a part with AFO status, a licence will also be required.

When to renovate and when to rebuild

Renovating usually pays off when the house is legal or nearly so, keeps square metres that could not be built today, the structure is sound and the layout can be opened up without touching the main structural elements.

Rebuilding usually pays off when the plan allows you to build more or better than what exists, the structure needs deep reinforcement, the house is badly oriented to the views or the sun, or the brief you have in mind does not fit the current floor plan.

There is a common third way in between: keep the structure and foundations, strip the interior and redo the façades, roof and services. That is a full refurbishment, and for many villas of this period it offers the best balance of cost, timing and result.

How we assess it

Before drawing anything we carry out a preliminary study: a visit to the house, a review of the planning and registry documents, an inspection of the structure and a comparison of both options against what the plan allows, what the code requires and an order of magnitude of cost and timing. If you have not bought yet, it is worth running the same checks as for buying a plot first.

If you are considering a villa in Marbella, Estepona or Benahavís, send us the address or the cadastral reference and we will tell you which option makes more sense before you commission any project.

Frequently asked questions

Can a villa with AFO status be extended?

Generally not. LISTA allows conservation and refurbishment works on these buildings, including consolidation, as long as they do not increase the footprint or the built volume. To extend, the irregular part would first have to be capable of legalisation under the current plan, and that has to be checked plot by plot.

Does a full refurbishment need a building licence?

Not always. In Andalucía, works on existing buildings on consolidated urban land that comply with the plan, or are legally non-conforming, and do not change the footprint, height, buildability or number of dwellings can be processed with a declaración responsable. If the works extend the house or affect an irregular part, a licence is required. Either way, a refurbishment that touches the structure or the façade needs a project by an architect.

Do I need a new energy certificate after renovating?

If the renovation is a major one, yes. For example, when more than a quarter of the thermal envelope is renewed or the heating and cooling installations are replaced, a new energy performance certificate reflecting the final state of the house is required.

Thinking of renovating a villa?

Send us the address or the cadastral reference and we will assess whether to renovate or rebuild.